Road Concreting, Tagbilaran City

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Specific

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

20,000,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

Implementation Period

DATE STARTED DATE COMPLETED
Jun 29, 2018 Oct 10, 2018

Budget Allocation

CURRENCY COST
20,000,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
June - 2018 October - 2018 100.0 100.0 Jul 30, 2018 Apr 3, 2019

Success Indicators

-No entries found

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Bohol District 1 Tagbilaran

List of supporting documents

-No entries found

-No entries found