Rehabilitation of Bacong Integrated Waterworks System, Bacong, Negros Oriental

PROJECT OVERVIEW

SOURCE OF FUNDS:

COVERAGE OF PROJECT:

Specific

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

10,000,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Water Resources

Project Description

Rehabilitation of Integrated Waterworks System

Implementation Period

DATE STARTED DATE COMPLETED
Apr 9, 2018 Sep 5, 2018

Budget Allocation

CURRENCY COST
10,000,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
April - 2018 September - 2018 100.0 100.0 May 17, 2018 Oct 20, 2018

Success Indicators

QUANTITY UNIT OF MEASURE DESCRIPTION
0 Project

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Negros Oriental District 3 Bacong