Construction/Rehabilitaion of Multi-purpose Building, Calango, Zamboanguita, Negros Oriental

PROJECT OVERVIEW

SOURCE OF FUNDS:

COVERAGE OF PROJECT:

Specific

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

3,000,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Social Infrastructure

Project Description

Completion of Multi-purpose Building

Implementation Period

DATE STARTED DATE COMPLETED
Feb 12, 2018 Jul 25, 2018

Budget Allocation

CURRENCY COST
3,000,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
February - 2018 June - 2018 76.72 62.23

-14.49

May 17, 2018 Jul 31, 2018

Success Indicators

QUANTITY UNIT OF MEASURE DESCRIPTION
0 Building

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Negros Oriental District 3 Zamboanguita Calango

List of supporting documents

-No entries found

-No entries found