Network Development - Off-Carriageway Improvement Panglao Island Circumferential Rd - (S00064BH) K0007 + 137 - K0008 + 000, (S00065BH) K0009 + 000 - K0010 + 000

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Districtwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Suspended

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

29,989,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

(S00064BH) K0007 + 137 - K0008 + 000, (S00065BH) K0009 + 000 - K0010 + 000

Implementation Period

DATE STARTED DATE COMPLETED
May 11, 2018 Sep 12, 2018

Budget Allocation

CURRENCY COST
29,989,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
May - 2018 September - 2018 28.5 28.5 Jul 31, 2018 Apr 3, 2019

Success Indicators

-No entries found

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Bohol District 1 All

List of supporting documents

-No entries found

-No entries found

The project is suspended. Subject for termination for default in contract for Infrastructure projects. Issued show cause orders dated, Jan. 19, 2019. Sent show cause order to the contractor dated, Feb. 7, 2019. Contractors reply letter dated, Feb. 23, 2019. Proceedings of termination is on-going.