Network Development - Off-Carriageway Improvement Tagbilaran North Rd (Tagbilaran-Jetafe Sect) - K0003 + 000 - K0006 + 060, K0011 + 000 - K0012 + 598, K0012 + 861 - K0013 + 386.70

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Districtwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

86,396,310

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

K0003 + 000 - K0006 + 060, K0011 + 000 - K0012 + 598, K0012 + 861 - K0013 + 386.70

Implementation Period

DATE STARTED DATE COMPLETED
Jun 14, 2018 Dec 24, 2018

Budget Allocation

CURRENCY COST
86,396,310

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
June - 2018 December - 2018 100.0 100.0 Jul 31, 2018 Apr 3, 2019

Success Indicators

-No entries found

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Bohol District 1 All