Asset Preservation of National Roads - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Sta Catalina-Pamplona-Tanjay City

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Districtwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

73,191,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

Station Limits: K0034 + 000 - K0035 + 000, K0038 + 172 - K0039 + 000, K0044 + 411 - K0044 + 508, K0047 + 271 - K0047 + 360, K0052 + 000 - K0052 + 066, K0054 + 000 - K0054 + 490

Implementation Period

DATE STARTED DATE COMPLETED
May 10, 2018 Feb 1, 2019

Budget Allocation

CURRENCY COST
peso 73,191,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
May - 2018 February - 2019 7.78 10.0

2.22

Jul 19, 2018 Jul 20, 2018
May - 2018 February - 2019 35.47 65.36

29.89

Sep 26, 2018 Sep 26, 2018
May - 2018 February - 2019 88.36 85.0

-3.36

Dec 28, 2018 Dec 28, 2018
May - 2018 February - 2019 97.99 96.0

-1.99

Mar 29, 2019 Mar 29, 2019
May - 2018 April - 2019 100.0 100.0 Jul 25, 2019 Jul 25, 2019

Success Indicators

QUANTITY UNIT OF MEASURE DESCRIPTION
0 meters Rehabilitation of Paved Road

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Negros Oriental District 2 All

List of supporting documents

-No entries found

-No entries found

Project is completed.