Asset Preservation of National Roads - Preventive Maintenance along Dumaguete North Rd (Dumaguete-Jct Bais-Kabankalan) - K0044 + 457 - K0047+ 190

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Districtwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

46,944,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

Implementation Period

DATE STARTED DATE COMPLETED
Mar 19, 2018 Jul 15, 2018

Budget Allocation

CURRENCY COST
46,944,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
March - 2018 July - 2018 16.0 16.26

0.26

May 16, 2018 May 16, 2018
March - 2018 July - 2018 100.0 95.0

-5.0

Jul 19, 2018 Jul 20, 2018
March - 2018 July - 2018 100.0 100.0 Sep 26, 2018 Sep 26, 2018

Success Indicators

QUANTITY UNIT OF MEASURE DESCRIPTION
0 lane km

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Negros Oriental District 2 All

List of supporting documents

-No entries found

-No entries found

Project is completed.