Dalaguete-Mantalongon-Badian Road, Brgy. Ablayan to Brgy. Dobdob Section (Package 1), Sta. 0+000-Sta.2+443, Cebu

PROJECT OVERVIEW

SOURCE OF FUNDS:

GAA - Local

COVERAGE OF PROJECT:

Regionwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

120,000,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

Implementation Period

DATE STARTED DATE COMPLETED
May 11, 2018 Mar 28, 2019

Budget Allocation

CURRENCY COST
120,000,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
May - 2018 March - 2019 61.01 51.33

-9.68

Jul 12, 2018 Feb 7, 2019

Success Indicators

-No entries found

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
0.0 0.0 Cebu District 2 All

List of supporting documents

-No entries found

-No entries found

On-going.