Construction of Tagbilaran City By-Pass

PROJECT OVERVIEW

SOURCE OF FUNDS:

COVERAGE OF PROJECT:

Regionwide

FUNDING AGENCY:

DPWH

IMPLEMENTING AGENCY:

STATUS OF PROJECT:

Completed

TYPE OF PROJECT:

Regular

TOTAL PROJECT COST:

130,000,000

TOTAL PROJECT COMPONENT COST:

SECTOR:

Infrastructure

SUB-SECTOR:

Transportation

Project Description

Implementation Period

DATE STARTED DATE COMPLETED
May 4, 2015 Feb 19, 2016

Budget Allocation

CURRENCY COST
130,000,000

Physical Accomplishments

START END TARGET ACCOMPLISHMENT (%) ACTUAL ACCOMPLISHMENT (%) SLIPPAGE (%) DATE INPUTTED DATE UPDATED
May - 2015 February - 2016 100.0 100.0 Feb 23, 2016 May 17, 2018

Success Indicators

-No entries found

Project Locations

LATITUDE LONGITUDE PROVINCE DISTRICT CITY/MUNICIPALITY BARANGAY SITIO
9.67731522159089 123.872754639844 Bohol District 1 Tagbilaran

List of supporting documents

-No entries found

-No entries found

Project Completed